"Decades of work in one decade." That's how Akron Mayor Shammas Malik described the city's sewer overhaul in a meeting with reporters, according to Signal Akron. In the same conversation he said the sewer system needs to fund itself, and that the new rate legislation "creates some level of consistency and expectation" for residents' bills.

That predictability matters if you're comparing homes and building a monthly budget, because most of the sewer bill for an Akron address through 2029 is already scheduled. Only one line is still open, and its fate is moving through federal court right now.

Akron sewer rates through 2029

In October 2025, Akron City Council voted 11 to 1 for a 5.3% annual increase in the sewer usage rate, plus a new fixed monthly charge. Ideastream Public Media reported that it was the first retail rate increase in 10 years for the system's 75,000 customers in the city and surrounding communities.

The city's own estimates assume an average residential customer using 400 cubic feet of water a month, which the city bills as 4 HCF. Here's the projected path for that household's sewer bill alone. Water service is billed separately.

Year Fixed monthly charge Typical monthly sewer bill Same bill if the $15 charge applies
2025 none $46.39 n/a
2026 $5.00 $53.63 n/a
2027 $5.00 $55.99 n/a
2028 $10.00 $63.51 $78.51
2029 $12.50 $68.65 $83.65

These are the city's projections, as Signal Akron reported in September 2025. The fixed charges apply to homes with water meters 5/8 inch to 1 inch, which covers most houses. Rates are higher for pipes larger than 1 inch, which usually means commercial properties.

From 2025 to 2029, the typical bill rises a little over $22 a month. If the extra charge in the last column takes effect, the rise is a little over $37. The city's September 2025 rate announcement spells out both scenarios.

Why the bill rises after construction ends

Akron's sewer bill keeps rising as the city finishes the last of the work it was required to do.

The 2014 federal consent decree with the U.S. EPA and Ohio EPA required 26 major projects to stop combined sewer overflows. Those happen when heavy rain overwhelms the old system and untreated sewage mixes with stormwater, then spills into the Little Cuyahoga River, the Cuyahoga River and the canal. Akron has finished 24 of the 26 projects. The 25th, the Northside Interceptor Tunnel, is under construction and scheduled to be done by the end of 2026.

According to the city, once that tunnel is done, 99% of wet-weather flow into the sewer system will have been eliminated or captured for full treatment. That keeps about 2.3 billion gallons a year of untreated wastewater out of local waterways.

The money explains the timing. The city says the consent-decree projects are funded by ratepayers and financed through long-term, low-interest loans. In other words, the tunnels and storage basins were built first, and ratepayers repay them over many years.

Akron's Public Service Director Chris Ludle told Ideastream that the increase is needed to cover the costs of more than 20 projects completed over the past decade. So the bill reflects how much has already been built and borrowed for. How much digging is left doesn't change it much.

For a home you're pricing today, the 2026 through 2029 increases are as close to a known cost as local utilities get. They were set by ordinance in October 2025 to repay work that is mostly finished.

The $15 charge that depends on a court

The one open piece is tied to the 26th project, a facility called the Enhanced High Rate Treatment plant, or EHRT. When the city proposed the new rates in 2025, it said a separate $15 fixed monthly charge would start in 2028 only if Akron had to build that plant.

The city has argued for years that the plant isn't needed, and the cost estimate has changed along the way. Ideastream reported more than $260 million in October 2025. A December 2025 city update put it at more than $265 million. The city's October 2026 announcement says over $300 million.

On Oct. 7, 2026, Akron announced it had reached agreement with both the U.S. EPA and Ohio EPA on a proposed Fourth Amendment to the consent decree. Under it, Akron would not build the EHRT. Instead, it would disinfect discharges from its wastewater treatment plant for two more months each year, April and November. The city says the plant would have treated only three overflows in a typical year. It also says disinfecting every day in those two months better protects people using the river for recreation.

The alternative has also changed. In December 2025, the city described converting the Cuyahoga Street Storage Facility into a treatment site for about $35 million. The October 2026 amendment describes the April and November disinfection plan.

What connects all of this to your bill is one sentence in that December 2025 update. If the court approves the amendment, the city says it "does not have to implement the $15 fixed charge on sewer bills beginning in 2028."

Here's where the approval process stands as of this week:

  1. Oct. 7, 2026: The U.S. Department of Justice lodged the proposed amendment with the U.S. District Court for the Northern District of Ohio.
  2. Oct. 14, 2026: The notice of lodging ran in the Federal Register. That started a 30-day public comment period.
  3. Nov. 13, 2026: Comments are due, according to the city's Akron Waterways Renewed consent decree page, which also posts the full text of the amendment.
  4. After the comment period: Depending on the comments received, the parties will ask the District Court to approve the amendment. The city says it isn't final unless and until the court approves it.

Coverage of the agreement from Cleveland.com, Spectrum News 1 and Ideastream called it a win for ratepayers. None of them gave a revised bill amount. Until the court acts, the 2028 and 2029 figures have two possible outcomes, and the table above shows both.

Using these numbers on a specific house

If you're comparing an Akron home with one in a neighboring community, the sewer line in your budget now rests on firmer ground than it did a year ago. A few details shape how it applies to a particular property:

  • Use your own usage. Every projection here assumes 4 HCF a month. A larger household, or a smaller one, will land above or below those figures because the 5.3% increase applies to the usage rate.
  • Expect the fixed charge to step up in 2028 either way. It doubles from $5 to $10 in 2028 whether or not the $15 charge applies.
  • Check where the address is. Akron's water bill assistance program gives eligible residents a 40% discount on the drinking-water portion of the bill. The 2025 sewer legislation extended a 40% discount on the total sewer bill to eligible homeowners and, for the first time, tenants. Eligibility is based on household income at or below 175% of federal poverty guidelines, or a Homestead Exemption. Both discounts are for Akron residents, so customers outside the city who are served by Akron utilities don't qualify.

This is general information, not legal, tax or financial advice. Confirm your own rates, eligibility and budget with the City of Akron and your lender before you rely on them.

The city's next priority is drinking water

The October 2026 announcement also signals where the city's attention goes next. Ludle said in the city's release, "We are reaching the end of that chapter, but our responsibility to maintain critical infrastructure does not end with it." The city says that as the consent-decree work wraps up, it will put more resources into its aging drinking-water system.

That shift is already in the budget. Signal Akron's coverage of the 2026 capital budget lists $102.2 million in planned water-system spending, including:

  • $23.6 million to replace the Brittain Road Reservoir
  • $13.5 million for water meters
  • $10.4 million for water mains
  • $3.2 million for an advanced treatment system

The same budget includes $12 million for lead-risk reduction. Signal Akron reported that the city finished removing all lead service lines the year before.

None of this sets a water rate. It does show where Akron's infrastructure money is heading after the sewer work.

Quick answers

Is the $15 charge officially gone? Not yet. The amendment that would let Akron skip the EHRT needs U.S. District Court approval after the comment period ends Nov. 13, 2026. The city has said that if the court approves it, the $15 charge won't take effect in 2028.

When does the Northside Interceptor Tunnel open? The city and Ideastream both say it's scheduled to be finished by the end of 2026.

How much has Akron spent on the sewer overhaul? The city's figures vary by announcement. The September 2025 release said over $1.2 billion, and the October 2026 release says ratepayers have invested over $1 billion.

If you'd like help building realistic monthly costs into a comparison of Akron homes, including utilities and the 2028 charge that's still pending, Nancy Bartlebaugh and the Bartlebaugh Team can walk through the numbers with you for the specific addresses on your list. Let's Connect.

Work With Nancy

I am eager to collaborate with you, offering my wealth of experience and commitment to making your real estate journey smooth, rewarding, and ultimately successful. Let's work together toward your goals.

Follow Me on Instagram